KLGKleyman Law GroupBusiness & Litigation Attorneys Free Case Analysis(212) 203-2082 KLGKleyman Law GroupBusiness & Litigation Attorneys
New York City construction site with work stopped behind a notice reading Work Temporarily Suspended

NYC Construction Dispute Lawyers

Lien, payment, delay and defect disputes for owners, contractors and subcontractors

Construction Claims We Bring and Defend

Mechanic's Lien Claims

We file and foreclose mechanic's liens for contractors, subcontractors, and material suppliers, and for owners and contractors we discharge liens that are defective, untimely, or exaggerated, by bond, deposit, or court order.

Payment Disputes & Withholding

A contractor or subcontractor can pursue money owed in contract against the party above it and, on covered projects, under the prompt payment statute. We collect unpaid balances and retainage, and defend withholding the contract supports.

Delay & Disruption Claims

Excusable, compensable, and concurrent delay carry different outcomes for schedule extensions and money damages. We pursue and defend delay and lost productivity claims on both sides of the contract.

Change Order Disputes

We pursue payment for extra work performed outside the original scope of work, and defend owners and contractors against change order claims that the contract or the project record does not support.

Bond & Surety Claims

Payment bonds, performance bonds, and lien discharge bonds create a route to recovery that does not depend on the owner's remaining funds. We prosecute and defend bond claims and pursue sureties that deny without basis.

Defect & Workmanship Claims

Substantial completion, punch list scope, and warranty terms frame the exposure on a defective work claim. We pursue defect claims for owners, and for contractors we defend them, including claims that a proposed repair would be a betterment.

Payment Dispute Exposure for Owners and Contractors

Exposure in a construction dispute depends on where a party sits in the payment chain. A contractor or subcontractor in a payment dispute has put its labor and materials into the building, and the statutory periods that protect its claim are already running.

An owner faces a lien on title for an amount nobody has tested, and has to decide whether to bond the lien or contest what is claimed. That decision turns on what the project record shows and what was still owed up the chain.

A general contractor can face claims from both directions at once, with the owner withholding payment above and subcontractors filing liens below.

How Construction Contract Disputes Start in New York

A construction contract dispute generally starts when one side does not follow a contract procedure while a problem is unfolding on the job, such as a notice provision, a written change procedure, or a payment condition, and the other side later argues that the failure is a breach of contract.

By the time the legal posture matters, the documentary record is already set. New York courts measure the claim against what the contract required at each step of the work and what the contemporaneous project records show.

Kleyman Law Group represents contractors, subcontractors, and property owners across Brooklyn, Queens, Manhattan, and Staten Island in disputes ranging from residential renovations to commercial buildouts. What begins as a payment dispute or a scope disagreement hardens into construction litigation when informal resolution fails and both sides reconstruct the project from documents.

Prompt Payment Rules for Private Construction Projects

New York's prompt payment statute governs private construction projects with an aggregate cost of $150,000 or more, counting all labor, services, materials, and equipment, and its payment rules reach the subcontracts on those projects. Public works and several categories of residential work fall outside it. An owner has twelve business days from delivery of an invoice and all contractually required documentation to approve or disapprove it, and thirty days after approval to pay. Late payment carries one percent monthly interest.

Retainage is capped at five percent of the contract sum, and a contract provision requiring more is void. The cap binds what an owner holds from a general contractor and what a general contractor holds from its subcontractors, and downstream retainage may not exceed what the owner retained. An owner must release retainage to the contractor within thirty days after final approval of the work.

A contractor may submit a final invoice for payment in full on reaching substantial completion, as the contract defines it. Where an owner fails to approve, disapprove, or pay within the statutory windows, the contractor may suspend performance after at least ten days' written notice and an opportunity to cure, and a subcontractor has a similar right on written notice to both the owner and the contractor.

The statute limits what the parties can negotiate away. Except in contracts with material suppliers, a clause applying another state's law or requiring a dispute to be resolved in another state is void, and so is a clause that bars suspension for nonpayment or takes away expedited arbitration. A party aggrieved by a prompt payment violation may refer it to expedited arbitration before the American Arbitration Association at least fifteen days after verified delivery of a written complaint to the other party.

Cause and Convenience Terminations in Construction

Termination rights live in the contract, and courts read the steps strictly. Where an agreement requires written notice and a period to cure, skipping that step generally makes the termination ineffective regardless of how poor the work was. The exceptions are narrow, reaching a party that repudiates the contract or abandons the work, or a breach that cannot be cured.

A defective termination costs more than the termination itself. A party that terminates without following the contract can lose the right to set off completion and remediation costs against what it still owes, which means funding the replacement contractor while answering for the outstanding balance.

Cause and convenience carry different exposure. A party terminated for convenience is generally limited to payment for work performed, while a party wrongfully terminated for cause can pursue a broader measure that includes lost profit on work never performed.

Many contracts include a conversion clause providing that a termination for cause becomes one for convenience where cause is not established later. Courts enforce that language, and exposure drops to the convenience measure. The contract's termination provisions also give the contractor its own right to end the work, typically conditioned on written notice.

Claims for Defective Construction Work

A defect claim turns on conformance. The question is what the contract documents and the applicable building code required, and whether the work as built departed from them. Aesthetic disappointment with conforming work generally supports no claim, and a deviation that causes no measurable damage supports very little.

The clock runs from completion of the work. A contract claim carries a six-year period that accrues when the work is finished, and a latent defect discovered years afterward does not restart it. New York sets no outright statute of repose for buildings, so the accrual date governs whether a claim survives.

New homes carry a statutory warranty on top of the contract, unless the contract excludes it by substituting a limited warranty that meets the statute's requirements. It covers skillful construction for one year, the plumbing, electrical, heating, cooling and ventilation systems for two years, and material defects for six years, each measured from the warranty date, which is the earlier of title passing to the first owner or first occupancy as a residence. Written notice must reach the builder before any action is commenced and no later than thirty days after the applicable period ends.

The owner must give the builder a reasonable opportunity to inspect, test, and repair the condition. On a condominium, the sponsor's obligation to correct defects in the common elements is set by the offering plan, which fixes its own notice windows.

Damages are measured by the cost to put the work right. The reasonable cost of repair or replacement is the ordinary measure, capped on a warranty claim at the replacement cost of the home excluding the land. Where repair would be disproportionate to the harm, a court can substitute the diminution in value.

Proof is built by experts on both sides. An owner establishing a defect shows what was required and how the work departed, then prices the correction, usually through an engineer or a licensed professional in the affected trade. A contractor defending one attacks causation and the scope of the proposed repair.

Mechanic's Lien Rights, Deadlines and Discharge

New York's Lien Law gives contractors, subcontractors, laborers, and material suppliers a claim against the improved property when construction work goes unpaid. A filed lien secures that claim against the owner's interest, subject to the statutory priority rules that govern competing interests in the property. The lien encumbers the property and generally must be satisfied, discharged, or bonded before a sale or refinancing closes free of it.

Recovery is capped by the funds owed up the chain. A subcontractor's lien reaches what the owner owed the general contractor when the notice of lien was filed, together with sums later earned under that contract. Where competing liens exceed that fund, claimants generally share it on a parity rather than by filing order, with laborers for daily or weekly wages paid first.

Filing deadlines run from the last date labor or materials were furnished. Most private improvements carry eight months and single-family dwellings four. Retainage carries its own window, ninety days after the retainage became due. A filed lien lasts one year unless a foreclosure action is commenced and a notice of pendency filed within that period, or the lien is extended.

An owner or contractor can remove a lien from the property without resolving the underlying claim. A bond equal to 110 percent of the lien amount, or a deposit of the claimed amount with interest, discharges the lien against the real property and shifts it to that substitute security. Discharge concedes nothing on the amount owed, and the claim must still be established in court before the lienor reaches those funds.

Lien amounts are tested in the enforcement action. A court that declares an otherwise valid lien void for willful exaggeration after trial can hold the filer liable for the bond premium or deposit interest, the attorney's fees spent securing the discharge, and the difference between the amount claimed and the amount actually due. The penalty is strictly construed and does not reach an honest error.

New York mechanic's lien deadlines drawn to scale A proportional timeline anchored on the lien filing date. Most private improvements carry eight months to file and single-family dwellings four months, both measured from the last labor or materials furnished. The owner must be served from five days before to thirty days after filing, and proof of service filed within thirty-five days. The lien then remains in force one year, within which a foreclosure action must be commenced or the lien extended. A lien for retainage alone may be filed within ninety days after the retainage became due. lien filed Most private improvements 8 months to file Single-family dwellings 4 months Serve the owner 5 days before to 30 days after filing File proof of service 35 days, or the lien terminates Lien remains in force 1 year to foreclose or extend 8 mo before 4 mo filing 4 mo after 8 mo 12 mo
Service and proof of service run on separate clocks, and the service window closes first.

Trust Fund Diversion Claims Under the Lien Law

Money received for a construction improvement is impressed with a statutory trust the moment it arrives. An owner drawing on a construction loan, a general contractor collecting a requisition, and a subcontractor receiving payment each hold those funds as trustee, to be applied to labor, materials, and related project costs before anything else.

Each improvement creates a separate trust, and so does each contract or subcontract a contractor or subcontractor performs. The trustee takes the beneficial interest only in what remains once the trust claims are paid or discharged. The trustee must keep books and records tracking trust assets, payments, and claims project by project, and those records are what a beneficiary examines when payment stops.

Applying trust money to another purpose is a diversion. Funding a different job, covering general overhead, or taking money out while project bills sit unpaid generally qualify. Officers, directors, and agents who participate are personally liable to the beneficiaries, and an intentional diversion left unpaid can carry criminal exposure under the Lien Law.

A beneficiary can compel an accounting before filing suit. On written demand the trustee must furnish a verified statement of the trust or permit examination of the books, and that demand carries procedural requirements that have to be followed exactly. Failing to keep the required records is itself presumptive evidence of a diversion.

Identifiable trust assets are generally not available to the contractor's ordinary creditors in bankruptcy. Those funds remain subject to beneficiary claims rather than passing to general creditors, which puts an unpaid subcontractor in a different position from an ordinary contract claimant, though tracing and commingling affect how the claim is established.

Trust claims reach parties a lien cannot. Where the lien fund owed up the chain is exhausted and the contracting company holds nothing worth collecting, a trust claim reaches the principals who moved the money. Enforcement carries its own conditions, including the requirement that the action proceed as a class action.

Arbitration or Litigation of Construction Disputes

Where a construction dispute is heard depends on what the contract says. New York enforces arbitration clauses under a long-standing policy favoring arbitration, and many contracts add mediation as a condition precedent that stays the arbitration or the lawsuit until the parties have met. Skipping a required step can delay a claim or expose it to dismissal.

Lien rights survive the contract's choice of forum. The Lien Law voids an agreement waiving the right to file or enforce a lien in advance, and a dispute resolution procedure that blocks a claimant from filing is unenforceable to that extent.

Arbitration and litigation trade different advantages. Arbitration is private and runs on its own schedule, though document exchange is narrower, which matters where a delay or defect claim turns on volume. Commercial litigation in court offers full discovery and a public record.

Where an award could be rendered ineffectual without interim relief, a court can grant an attachment or a preliminary injunction in aid of an arbitration that is pending or about to begin. The order lapses if the arbitration is not commenced within thirty days, unless the court sets a different period.

Have a Lien, Payment or Defect Dispute Reviewed by Litigators

Common Questions About Construction Disputes

New York City requires a Department of Consumer and Worker Protection home improvement contractor license for residential work costing more than $200. An unlicensed contractor can neither enforce the contract nor recover in quantum meruit for the value of the work, and CPLR 3015(e) subjects a complaint to dismissal where it fails to plead compliance. The bar reaches lien rights as well, so an unlicensed contractor cannot enforce a mechanic's lien for the same work. The requirement excludes new home construction, purely plumbing or electrical work, which run under separate Department of Buildings licenses, and work in buildings with more than four units other than in the unit the owner or tenant lives in.
A subcontractor's right to recover against an owner is generally derivative of the general contractor's right to recover. Where the general contractor lacked the license the local law required, courts have held that the subcontractor cannot reach the owner either, leaving the subcontractor to pursue the general contractor directly.
A home improvement contract with an aggregate price over $500 must be in writing and signed by all parties (General Business Law §§ 770, 771). It must state, among other terms, the contractor's name, address, telephone number and any license number, the approximate dates the work will begin and be substantially completed, a description of the work and materials, the agreed price, and any schedule of progress payments. It must include notice of the owner's right to cancel until midnight of the third business day after signing, and notice that payments received before completion must be deposited as Lien Law § 71-a requires unless the contractor posts a bond, contract of indemnity, or irrevocable letter of credit.
Lien Law § 11 requires the lienor to serve a copy of the notice of lien on the owner within five days before or thirty days after filing it, and to file proof of that service with the county clerk within thirty-five days after filing. Failure to file the proof within thirty-five days terminates the notice as a lien. Until service is made, an owner without knowledge of the lien is protected in any payment it makes in good faith.
Yes. Lien Law § 3 gives a lien to a contractor, subcontractor, laborer, or material supplier who performs labor or furnishes materials for an improvement with the consent or at the request of the owner, or of the owner's agent, contractor, or subcontractor. The statute does not require a written contract.
Yes. Under Lien Law § 19(6), the owner or another party in interest can petition the court to summarily discharge a lien where the notice of lien does not comply with Lien Law § 9, where the public record shows it was not filed as Lien Law § 10 requires, or where it appears from the face of the notice of lien that the labor or materials furnished carry no lien. The application is made on a verified petition with written proof, served on the lienor at least five days before the hearing.
Yes. Under Lien Law § 59, a notice served on the lienor can require it to commence an action to enforce the lien within a time stated in the notice, not less than thirty days from service, or to show cause in the county where the property is located why the lien should not be vacated. The notice is served personally or left at the lienor's last known place of residence with a person of suitable age, with directions to deliver it to the lienor. On an affidavit proving service and showing that no foreclosure action was commenced as directed, a court can vacate and cancel the lien.
Yes. Under Lien Law § 17, the lienor can file an extension with the county clerk within one year after the original notice of lien was filed, continuing the lien for up to one more year. A lien on property with a single-family dwelling can be extended only by court order. If no foreclosure action is commenced within the extended period, the lien is extinguished unless a court order continues it.
Recovery turns on critical path proof. A schedule analysis compares the as-planned sequence against the as-built record to isolate which activities drove the completion date and which party caused them. For disruption and lost productivity, a measured mile analysis compares output on impacted work against output on comparable unimpacted work. Where the contract requires notice of delay, the notice generally has to be given while the delay is occurring, and a claim first raised at closeout invites the defense that the notice condition was not met.
Generally yes. New York enforces clear no-damage-for-delay provisions, and the party challenging one carries a heavy burden. Recovery remains available in four narrow situations: delay caused by bad faith or willful, malicious, or grossly negligent conduct; delay the parties did not contemplate; delay so unreasonable that it amounts to intentional abandonment of the contract; and delay resulting from breach of a fundamental contractual obligation. Courts read these exceptions narrowly and dismiss claims pleaded in conclusory terms. Relabeling a delay claim as lost productivity does not move it outside the clause.
It depends on the contract and the conduct. Construction contracts typically require written authorization signed by a designated representative before extra work is compensable. A course of conduct in which the parties routinely performed and paid for unsigned changes can waive that requirement, and the waiver is proved through the project record, such as daily reports and requisitions that paid earlier unsigned changes.
A lien foreclosure is tried in the county where the property sits (CPLR 507). A construction contract claim can be venued in a county where a party resides or where a substantial part of the events occurred (CPLR 503(a)). Assignment to the Commercial Division depends on the county threshold set by Uniform Rule 202.70, currently $500,000 in New York County, $150,000 in Kings, $100,000 in Queens, and $75,000 in Bronx. Home improvement contracts involving one- to four-unit residential properties, or individual units in any residential building, including co-op and condominium units, are excluded regardless of the amount.
Generally not. New York follows the American rule, under which each side bears its own fees unless a statute, court rule, or the contract itself provides otherwise. A prevailing party clause in the construction contract is the usual route, and it applies to whichever side prevails.